Location | Western Province, Gampaha District, Attanagalla Divisional Secretariat |
Year of Commencement | 1999 |
Distance from Colombo | 42 km |
Total Extent | 123 Acres |
Industrial Area | 67.84 Acres |
Worker Population | 10436 (Female: 6838, Male:3598) |
Specialization of Zone | Greenery Zone located at Gampaha district near to the Colombo Kandy Highway and close proximity to Colombo Kandy Expressway, accommodating enterprises from different sectors. |
Zone Information | |
|
Western Province, Gampaha District, Attanagalla Divisional Secretariat |
|
Common bus and other vehicles parking facility, Public Transport facility. |
|
49.78 Ha (123 Acres) |
|
Low polluting industries would be located. Sewage and effluent collection system, Common Wastewater treatment system, Stormwater disposal, and landscaping. Greenery environment |
|
Asphalt paved road access available to all plots. |
|
Security lighting and Chain link fencing 24hrs X 07 days security and Fire Service. |
|
300 lines for local calls, IDD, and facsimile, Internet facilities, Fiber optic lines |
|
Total water requirement of the Zone is 1450 m3/day, 700 m3 per obtained Ranpokunagama water supply scheme, 200 m3 from tube well and transport from Mirigama by the Wathupitiwala zone and the enterprises. |
|
8MVA through grid substation |
|
Units of servicing departments of the BOI & utility management organizations housed in BOI Administrative Complex. |
Zone Information
| Western Province, Gampaha District, Attanagalla Divisional Secretariat |
| Common bus and other vehicles parking facility, Public Transport facility. |
| 49.78 Ha (123 Acres) |
| Low polluting industries would be located. Sewage and effluent collection system, Common Waste water treatment system, Storm water disposal and landscaping. Greenery environment |
| Asphalt paved road access available to all plots. |
| Security lighting and Chain link fencing , 24hrs X 07 days security and Fire Service. |
| 300 lines for local calls, IDD, and facsimile, Internet facilities, Fiber optic lines |
| Total water requirement of the Zone is 1450 m3/day, 700 m3 per obtained Ranpokunagama water supply scheme, 200 m3 from tube well and transport from Mirigama by the Wathupitiwala zone and the enterprises. |
| 8MVA through grid substation |
| Units of servicing departments of the BOI & utility management organizations housed in BOI Administrative Complex. |
Land Premium | US $50,000.00 (Minimum Rate / Period of lease – 30 years) |
Ground Rent | US $ 4,660.00 per acre per annum |
Water Charges | Rs. 75.00 per m3 + Monthly Service Charge |
Waste Water Charges | |
From 01 April 2022 | Rs. 30.00 (Per cm3) |
From 01 January 2023 | Rs. 40.00 (Per cm3) |
From 01 January 2024 | Rs. 50.00 (Per cm3) |
Solid Waste Disposal Charges | Rs.7,250.00 per Metric Ton |
- 8MVA through grid substation
- Total water supply to the Zone is 1450 m3/day, 700 m3 obtain from Ranpokunagama water supply scheme, 200 m3 from tube well and transport from Mirigama by the Wathupitiwala zone and the enterprises.
- 300 lines for local calls, IDD, facsimile, Internet facilities, and Fiber-optic lines.
- Asphalt paved road access available to all plots
- Sewage and effluent collection system, treatment system, stormwater disposal and landscaping
- Solid waste disposal facility
Services Provided by BOI |
|
Services Provided by other State Agencies | – |
Available commercial facilities | Bank A T M machines available within the zone |
Average current market salary scales for following positions in manufacturing sector in BOI Enterprises (As at November 2020)
In Western Province | In Other Provinces | |||
SLR | US$ | SLR | US$ | |
(184.31 – ER) | (184.31-ER) | |||
Factory Plant Level | ||||
Trainee | 15,000.00 | 81.38 | 13,500.00 | 73.25 |
Unskilled | 18,000.00 | 97.60 | 13,500.00 | 73.25 |
Semiskilled | 20,000.00 | 108.50 | 15,000.00 | 81.38 |
Skilled | 35,000.00 | 189.89 | 30,000.00 | 162.76 |
Supervisory | 40,000.00 | 217.00 | 35,000.00 | 189.89 |
Technical (Non Executive) | 40,000.00 | 217.00 | 35,000.00 | 189.89 |
Technical (Executive) | 45,000.00 | 244.15 | 40,000.00 | 217.02 |
Manager | 150,000.00 | 813.84 | 130,000.00 | 705.30 |
Senior Manager | 250,000.00 | 1356.40 | 200,000.00 | 1085.12 |
Office / Administrative Level | ||||
Office Aide | 18,000.00 | 97.60 | 16,000.00 | 86.80 |
Clerical & Allied | 30,000.00 | 162.76 | 25,000.00 | 135.64 |
Executives | 40,000.00 | 217.00 | 35,000.00 | 189.89 |
Manager | 125,000.00 | 678.20 | 100,000.00 | 542.56 |
Senior Manager | 175,000.00 | 949.48 | 150,000.00 | 813.84 |
Mr H G B P U Silva
Senior Deputy Director
Mobile : +94 773422933